You are not logged in.
Pages: 1
The way we are using the project plugin (current version on 0.83.2) we use tasks to show long term groupings of tasks (i.e. if the project is "build a house" then a task might be "build bathroom" with a duration of some number of days and tasks underneath that for individual items like "install sink") This way we can see a gantt chart of the planned project with dates and durations with out creating a bunch of sub projects. Unfortunately, this means that all of these tasks show up every hour of every day on the calendar and makes the planning calendar useless. Is there a way to suppress the project tasks from the calendar? I can't seem to find an option similar to the "display on gantt" option that is for the calendar...
Thanks!
Offline
Is there a way to suppress the project tasks from the calendar? I can't seem to find an option similar to the "display on gantt" option that is for the calendar...
Thanks!
Hi, I have the same problem : I need to undisplay a task too.
French translation :
Bonjour, j'ai le même problème : j'aurais besoin de supprimer/masquer des planifications dans le plugin Projet (version 1.3.1) pour rendre le calendrier lisible.
(J'ajoute une référence à ce post dans la section des plugins)
Merci/Thanks
Emmanuel
Offline
Pages: 1