We started with 0.85.2 because of project management features. Initially we decided for WBS structure represented as follows:
Project
(Subprojects)
Tasks
(Subtasks)
Tickets
There are some issues with that, but we think there is a bug in structure display with Gantt provided we have SUBprojects. In that case the tasks are not situated below the "fathers", but somewhere stohastic.
2) problem in Gantt is that only some 20 characters of project name beginning are displayed and some 10 characters of task name! Completely unusable.
3) In Gantt no tickets display is possible - this doesn´t correspond to complete WBS representing.
Last edited by madjaric (2015-04-05 11:21:19)
Miro
Offline
Ok, I found the bug-rule: tasks in Gantt are ordered not depending on structure, but on starting date!???
Here the screenshot:
Thus task 2.2, the child of 2. subproject, should come at the end!
Evidence for this assumption is here, task 2.2 date shifted in the future:
I think this is a serious error, ordering Gantt elements accotding to time and not according to WBS! Pls do correct this!
Last edited by madjaric (2015-04-06 09:08:22)
Miro
Offline
No I tested it on demo GLPI site: result is the same:
Task within subroject should be under subproject, but is positionad above because of an earlier start date!
This is a substantial problem, because the Gantt is the only way to display WBS, or is there any other means for that?
In general, substantuially better control of WBS has to be implemented!
Last edited by madjaric (2015-04-06 14:50:09)