#1 2024-11-11 21:59:21

mecmav
Member
From: Brasil
Registered: 2019-03-22
Posts: 330

10.0.16 - Planning - strange behavior

I am testing the insertion of planning in glpi (Assistance > Planning).

In version 9.5.13 I can create a plan with a start date of 11:00 and a period of 6 hours without a repetition rule.

When I try to clone this planning, the cloned copy is created with exactly the same period and start date options.

When doing the same process in glpi 10.0.16, when I clone the planning, the clone copy is created with the start date 4h earlier, that is, 7am.

I've already checked the timezone settings and it's configured correctly.

Could this be a bug in this version of glpi?

Last edited by mecmav (2024-11-12 13:48:43)

Offline

#2 2024-11-12 14:06:23

mecmav
Member
From: Brasil
Registered: 2019-03-22
Posts: 330

Re: 10.0.16 - Planning - strange behavior

Setup > General > Default values

When I use a timezone -4 it it happens when i try to clone a planning.
If a set a timezone +0 the clone is done with the same start hour (that's is correct).

Is a use the timezone = server configuration, the planning is cloned with a -4h start date in relation at the parent planning.

It's happening in this glpi 10.0.16.

In the 9.5.13 it's ok, even with the timezone -4

Offline

#3 2024-11-12 15:43:56

mecmav
Member
From: Brasil
Registered: 2019-03-22
Posts: 330

Re: 10.0.16 - Planning - strange behavior

I made a test in version 10.0.17, and still happening

Offline

#4 2024-11-12 20:52:36

mecmav
Member
From: Brasil
Registered: 2019-03-22
Posts: 330

Re: 10.0.16 - Planning - strange behavior

Someone can confirm if this is a bug ?