You are not logged in.
I am testing the insertion of planning in glpi (Assistance > Planning).
In version 9.5.13 I can create a plan with a start date of 11:00 and a period of 6 hours without a repetition rule.
When I try to clone this planning, the cloned copy is created with exactly the same period and start date options.
When doing the same process in glpi 10.0.16, when I clone the planning, the clone copy is created with the start date 4h earlier, that is, 7am.
I've already checked the timezone settings and it's configured correctly.
Could this be a bug in this version of glpi?
Last edited by mecmav (2024-11-12 13:48:43)
Offline
Setup > General > Default values
When I use a timezone -4 it it happens when i try to clone a planning.
If a set a timezone +0 the clone is done with the same start hour (that's is correct).
Is a use the timezone = server configuration, the planning is cloned with a -4h start date in relation at the parent planning.
It's happening in this glpi 10.0.16.
In the 9.5.13 it's ok, even with the timezone -4
Offline
I made a test in version 10.0.17, and still happening
Offline
Someone can confirm if this is a bug ?
When the timezone is less than 0 (-1, -2, -3), if a planning need to be cloned, the cloned planning have the start-date different from the parent planning
Offline