I am saving several projects in GPLI. I also use the GANTT function but when I click the GANTT button the start date of all my projects is set to 2021-06-21. When i click a seperate project i see the correct dat. How can I fix this and make sure the dates on the GANTT are the correct dates?
Offline
Which version of GLPI are you using?